Work Details

Safety Precautions

All items must be checked before work commences. Mark each item as Required (Y/N) then confirm compliance.

Safety check Required? Y N
Work area defined with restricted access to unauthorised persons
If working at height, has a Permit to Work at Height been completed?
Safety bunting / flashing lights / permanent barriers are in place
Are persons working at height trained?
If isolation is completed, this is done by the LOTO procedure using hasps, locks and signage
If using scissor lift / MEWP, are persons trained?
Isolation of the crane or control pendant is taken up at height with engineer to prevent usage whilst under inspection / repair
There is 1 person on the ground to coordinate works and to prevent any unauthorised access
If cranes are isolated, has all supervision in the area been notified?